[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141571,799,1,"单选题","施工单位的项目施工质量计划或施工组织设计的编制与审批，应根据（ ）质量管理程序性文件规定的权限和流程进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","国家",false,{"key":16,"text":17,"correct":18},"B","企业",true,{"key":20,"text":21,"correct":14},"C","行业",{"key":23,"text":24,"correct":14},"D","国际","本题主要考查施工质量计划的审批程序。 施工单位的项目施工质量计划或施工组织设计文件编成后，应按照工程施工管理程序进行审批，包括施工企业内部的审批和项目监理机构的审查。企业内部的审批是指施工单位的项目施工质量计划或施工组织设计的编制与审批，应根据企业质量管理程序性文件规定的权限和流程进行。通常是由项目经理部主持编制，报企业组织管理层批准，并报送项目监理机构核准确认。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]