[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141564":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141564,799,2,"多选题","下列各项工作中，属于施工质量事后控制的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分项工程质量验收",true,{"key":16,"text":17,"correct":14},"B","分部工程质量验收",{"key":19,"text":20,"correct":21},"C","隐蔽工程质量验收",false,{"key":23,"text":24,"correct":14},"D","单位工程质量验收",{"key":26,"text":27,"correct":14},"E","已完施工成品保护","ABDE","本题考核的是事后控制的内容。 施工质量的事后控制，主要是进行已完施工的成品保护、质量验收和不合格的处理，以保证最终验收的建设工程质量。包括： （1）已完施工成品保护； （2）施工质量检查验收，从施工作业工序开始，依次做好检验批、分项工程、分部工程及单位工程的施工质量验收。 综上所述，正确选项为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]