[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141562":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141562,799,2,"多选题","建设工程施工质量的事后控制是指（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质量活动结果的评价和认定",true,{"key":16,"text":17,"correct":18},"B","质量活动的检查和监控",false,{"key":20,"text":21,"correct":18},"C","质量活动的行为约束",{"key":23,"text":24,"correct":14},"D","质量偏差的纠正",{"key":26,"text":27,"correct":14},"E","已完施工的成品保护","ADE","本题主要考查施工质量的事后控制途径。 事后质量控制是使不合格的工序或者最终产品（包括单位工程或整个工程项目）不流入下道工序、不进入市场。事后控制包括对质量活动结果的评价、认定；对工序质量偏差的纠正；对不合格产品进行整改和处理。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]