[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141559,799,1,"单选题","通过对施工全过程、全面的质量监督管理，保证整个施工过程及其成果达到项目决策所确定的质量标准，这是施工阶段质量控制的目标中（ ）的控制目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":18},"B","建设单位",true,{"key":20,"text":21,"correct":14},"C","监理单位",{"key":23,"text":24,"correct":14},"D","设计单位","本题主要考查施工阶段质量控制的任务目标。 建设单位的控制目标：建设单位在施工阶段，通过对施工全过程、全面的质量监督管理，保证整个施工过程及其成果达到项目决策所确定的质量标准。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]