[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141555":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141555,799,1,"单选题","建设单位在施工阶段进行施工质量控制的目标是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确保竣工项目达到投资决策确定的质量标准",true,{"key":16,"text":17,"correct":18},"B","确定施工质量达到优良标准",false,{"key":20,"text":21,"correct":18},"C","确保工程施工质量不出现质量缺陷",{"key":23,"text":24,"correct":18},"D","确保施工活动的正常进行","本题考核的是施工阶段质量控制的任务目标。 建设单位的控制目标是通过对施工全过程、全面的质量监督管理、协调和决策，保证竣工项目达到投资决策所确定的质量标准。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]