[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141547":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141547,799,2,"多选题","根据建设工程全过程质量管理的要求，质量控制的主要过程包括（ ）。 2016",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目策划与决策过程",true,{"key":16,"text":17,"correct":14},"B","设备材料采购过程",{"key":19,"text":20,"correct":14},"C","施工组织与实施过程",{"key":22,"text":23,"correct":24},"D","项目运行与维修过程",false,{"key":26,"text":27,"correct":14},"E","工程质量的评定过程","ABCE","本题考查的是全面质量管理思想和方法的应用。全过程质量管理的主要过程包括：项目策划与决策过程；勘察设计过程；设备材料采购过程；施工组织与实施过程；检测设施控制与计量过程；施工生产的检验试验过程；工程质量的评定过程；工程竣工验收与交付过程；工程回访维修服务过程等。参见教材68。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]