[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141543":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141543,799,1,"单选题","PDCA循环中，（ ）是处置阶段的主要任务。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","明确目标并制定实现目标的计划方案",false,{"key":16,"text":17,"correct":14},"B","展开工程的技术活动",{"key":19,"text":20,"correct":14},"C","对计划实施过程进行各种管理",{"key":22,"text":23,"correct":24},"D","对质量问题进行原因分析，采取措施予以纠正",true,"本题主要考查PDCA循环。 质量管理的PDCA循环是指： D项：对质量问题进行原因分析，采取措施予以纠正属于A（处置）阶段的措施。所以D项正确。 A项: 明确目标并制定实现目标的计划方案属于P（计划）阶段的措施。所以A项错误。 B项：展开工程的技术活动属于D（实施）阶段的措施。所以B项错误。 C项：对计划实施过程进行各种管理属于D（实施）阶段的措施。所以C项错误。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]