[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141542":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141542,799,1,"单选题","质量管理的PDCA循环中，“D”的职能是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","将质量目标值通过投入产出活动转化为实际值",true,{"key":16,"text":17,"correct":18},"B","对质量检查中的问题或不合格及时采取措施纠正",false,{"key":20,"text":21,"correct":18},"C","确定质量目标和制定实现质量目标的行动方案",{"key":23,"text":24,"correct":18},"D","对计划执行情况和结果进行检查","本题考核的是质量管理的PDCA循环。 质量管理的PDCA循环中，“D”指的是实施（Do），实施职能在于将质量的目标值，通过生产要素的投入、作业技术活动和产出过程，转换为质量的实际值。 综上所述，正确选项为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]