[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141540,799,1,"单选题","在PDCA循环中，P阶段的职能包括（ ）等。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定质量改进目标，制定改进措施",false,{"key":16,"text":17,"correct":18},"B","明确质量要求和目标，提出质量管理行动方案",true,{"key":20,"text":21,"correct":14},"C","采取应急措施，解决质量问题",{"key":23,"text":24,"correct":14},"D","规范质量行为，组织质量计划的部署和交底","本题主要考查PDCA循环的含义。 B项：由上表可知，明确质量要求和目标，提出质量管理行动方案属于P阶段的职能，故B项正确。 AC项：属于处置阶段的职能，故AC错误。 D项：属于实施阶段的职能，故D错误。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]