[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141538":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141538,799,1,"单选题","下列质量管理的职能活动中，属于PDCA 循环中\"D\"职能的活动是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","制定实现质量目标的行动方案",false,{"key":16,"text":17,"correct":14},"B","明确项目质量目标",{"key":19,"text":20,"correct":14},"C","专职质检员检查产品质量",{"key":22,"text":23,"correct":24},"D","行动方案的部署和交底",true,"本题考核的是质量管理的PDCA循环。 PDCA循环中的“P”职能是计划，“D”职能是实施，“C”职能是检查，“A”职能是处置。实施职能（\"D\"职能）在于将质量的目标值，通过生产要素的投入、作业技术活动和产出过程，转换为质量的实际值。在各项质量活动实施前，要根据质量管理计划进行行动方案的部署和交底。 D项：行动方案的部署和交底属于\"D\"职能的活动。故D项正确。 AB项：属于“P”职能的活动。故AB项错误。 C项：属于“C”职能的活动。故C项错误。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]