[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141499":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141499,799,1,"单选题","建立项目质量控制体系时，首先开展的工作是（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","分析质量控制界面",false,{"key":16,"text":17,"correct":14},"B","编制质量控制计划",{"key":19,"text":20,"correct":14},"C","制定质量控制制度",{"key":22,"text":23,"correct":24},"D","确立系统质量控制网络",true,"本题考查的是项目质量控制体系的建立。项目质量控制体系的建立过程，一般可按以下环节依次展开工作：(1)确立系统质量控制网络；(2)制定质量控制制度；(3)分析质量控制界面；(4)编制质量控制计划。所以选A。参见教材73。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]