[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141496":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141496,799,1,"单选题","关于项目质量控制体系的说法，正确的是（ ）。2014",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目质量控制体系需要第三方认证",false,{"key":16,"text":17,"correct":14},"B","项目质量控制体系是一个永久性的质量管理体系",{"key":19,"text":20,"correct":14},"C","项目质量控制体系既适用于特定项目的质量控制，也适用于企业的质量管理",{"key":22,"text":23,"correct":24},"D","项目质量控制体系涉及项目实施过程所有的质量责任主体",true,"本题考查的是项目质量控制体系。项目质量控制体系涉及项目实施过程所有的质量责任主体，而不只是针对某一个承包企业或组织机构，其服务的范围不同。参见教材72。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]