[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141494":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141494,799,1,"单选题","建立项目质量控制体系的过程包括：①分析质量控制界面；②确立系统质量控制网络；③制定质量控制制度；④编制质量控制计划。其正确的工作步骤是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","②→③→①→④",true,{"key":16,"text":17,"correct":18},"B","①→②→③→④",false,{"key":20,"text":21,"correct":18},"C","②→①→③→④",{"key":23,"text":24,"correct":18},"D","①→③→②→④","本题考查的是项目质量控制体系的建立。项目质量控制体系的建立过程，一般可按以下环节依次展开工作：（1）确立系统质量控制网络；（2）制定质量控制制度；（3）分析质量控制界面；（4）编制质量控制计划。参见教材71～172。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]