[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141492":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141492,799,2,"多选题","在大型群体工程项目中，第一层次质量控制体系可由（ ）的项目管理机构负责建立。( 2015真题 )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","涉及总责任单位",false,{"key":20,"text":21,"correct":14},"C","代建单位",{"key":23,"text":24,"correct":18},"D","施工总承包单位",{"key":26,"text":27,"correct":14},"E","工程总承包企业","ACE","本题考查的是项目质量控制体系的建立和运行，第一层次的质量控制体系应由建设单位的工程项目管理机构负责建立，在委托代建、委托项目管理或实行交钥匙式工程总承包的情况下，应由相应的代建方项目管理机构、受托项目管理机构或工程总承包企业项目管理机构负责建立。参见教材72。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]