[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141486":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141486,799,2,"多选题","建设工程项目的实施涉及到（ ）等多方主体的活动。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","政府主管部门",false,{"key":16,"text":17,"correct":18},"B","业主",true,{"key":20,"text":21,"correct":18},"C","监理单位",{"key":23,"text":24,"correct":18},"D","设计单位",{"key":26,"text":27,"correct":18},"E","供应商","BCDE","本题主要考查建设工程项目质量控制体系。 建设工程项目的实施，涉及到业主、设计单位、施工单位、监理单位、供应商等多方主体的活动，他们各自承担建设工程项目的不同实施任务和质量责任。因此，为了有效进行系统、全面的质量控制，必须由建设工程项目实施的总负责单位，负责质量控制系统的建立和运行，实施质量目标的控制。 综上所述，本题正确答案为BCDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]