[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141484":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141484,799,2,"多选题","建设工程项目质量控制系统运行的约束机制，取决于（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","各质量责任主体对利益的追求",false,{"key":16,"text":17,"correct":18},"B","各主体内部的自我约束能力",true,{"key":20,"text":21,"correct":14},"C","质量信息反馈的及时性和准确性",{"key":23,"text":24,"correct":18},"D","外部的监控效力",{"key":26,"text":27,"correct":14},"E","工程项目管理文化建设的程度","BD","本题考查的是建设工程项目质量控制体系的运行机制中约束机制的内容。 约束机制取决于各主体内部的自我约束能力和外部的监控能力。 BD项：BD项均为约束机制的内容，故为正确选项。 A项：A项属于动力机制的内容，故不当选。 C项：C项属于反馈机制的内容，故不当选。 E项：E项属于持续改进机制的内容，故不当选。 综上所述，本题正确选项为BD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]