[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141483":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141483,799,2,"多选题","一般情况下，建设工程项目质量控制系统应由（ ）的工程项目管理机构负责建立。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":14},"B","工程项目总承包企业",{"key":19,"text":20,"correct":21},"C","设计单位",false,{"key":23,"text":24,"correct":21},"D","施工企业",{"key":26,"text":27,"correct":21},"E","监理单位","AB","本题主要考查建设工程项目质量控制系统的建立。 一般情况下，建设工程项目质量控制系统应由建设单位、工程项目总承包企业的工程项目管理机构负责建立。 综上所述，本题正确答案为AB。 *",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]