[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141468":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141468,799,1,"单选题","建设工程项目质量控制系统总目标的分解，是根据控制系统内工程项目的分解结构，将工程项目的（ ）和质量总体目标分解到各个责任主体。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设标准",true,{"key":16,"text":17,"correct":18},"B","建设任务",false,{"key":20,"text":21,"correct":18},"C","管理工作",{"key":23,"text":24,"correct":18},"D","质量责任","本题主要考查目标分解原则。 建设工程项目质量控制系统总目标的分解，是根据控制系统内工程项目的分解结构，将工程项目的建设标准和质量总体目标分解到各个责任主体，明示于合同条件，由各责任主体制定出相应的质量计划，确定其具体的控制方式和控制措施。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]