[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141441,799,1,"单选题","项目干系人的质量控制应围绕着致力于满足（ ）的质量总目标而展开。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","规范规定",false,{"key":16,"text":17,"correct":18},"B","业主要求",true,{"key":20,"text":21,"correct":14},"C","参建方各自确定",{"key":23,"text":24,"correct":14},"D","质量监督机构提出","本题主要考查对质量控制的理解。 根据《质量管理体系标准》（GB／T19000-ISO9000（2000））中质量术语的定义：“质量控制是质量管理的一部分，致力于满足质量要求的一系列相关活动”。由于建设工程项目的质量要求是由业主提出的，因此，项目干系人的质量控制均应围绕着致力于满足业主要求的质量总目标而展开。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]