[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141424":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141424,799,2,"多选题","下列影响建设工程项目质量的因素中，属于可控因素的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","人的因素",true,{"key":16,"text":17,"correct":14},"B","技术因素",{"key":19,"text":20,"correct":21},"C","社会因素",false,{"key":23,"text":24,"correct":14},"D","管理因素",{"key":26,"text":27,"correct":14},"E","环境因素","ABDE","本题主要考查建设工程项目质量的影响因素。 建设工程项目质量的影响因素包括人、技术、管理、环境、社会五个方面。其中人、技术、管理和环境因素，对于建设工程项目而言是可控因素；社会因素存在于建设工程项目系统之外，一般情形下对于建设工程项目管理者而言，属于不可控因素，但可以通过自身的努力，尽可能做到趋利去弊。 综上所述，本题正确选项为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]