[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141423":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141423,799,2,"多选题","决定建设工程项目质量目标的主要依据是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","监理单位的要求",false,{"key":16,"text":17,"correct":18},"B","法律法规的要求",true,{"key":20,"text":21,"correct":14},"C","总承包企业的规划",{"key":23,"text":24,"correct":18},"D","业主的需求",{"key":26,"text":27,"correct":14},"E","设计单位的需求","BD","本题主要考查质量目标的依据。 决定建设工程项目质量目标的主要依据是：（1）业主的要求；（ 2）法律法规的要求。 综上所述，本题正确选项为BD项。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]