[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141413":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141413,799,1,"单选题","在建设工程项目质量的形成过程中，应在建设项目的（ ）阶段完成质量需求的识别。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计",false,{"key":16,"text":17,"correct":14},"B","竣工验收",{"key":19,"text":20,"correct":21},"C","决策",true,{"key":23,"text":24,"correct":14},"D","施工","本题主要考查建设工程质量的形成过程。 建设项目决策阶段的质量职能在于识别建设意图和需求，对建设项目的性质、建设规模、使用功能、系统构成和建设标准要求等进行策划、分析、论证，为整个建设项目的质量总目标以及建设项目内各个子项目的质量目标提出明确要求。因此，质量需求的识别应在决策阶段完成。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]