[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141412":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141412,799,1,"单选题","影响建设工程项目质量的管理因素主要是决策因素和（ ）因素。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织",true,{"key":16,"text":17,"correct":18},"B","设计",false,{"key":20,"text":21,"correct":18},"C","实施",{"key":23,"text":24,"correct":18},"D","技术","本题主要考查建设工程项目质量的影响因素分析。 影响建设工程项目质量的管理因素，主要是决策因素和组织因素。其中，决策因素首先是业主方的建设工程项目决策，其次是建设工程项目实施过程中，实施主体的各项技术决策和管理决策。管理因素中的组织因素，包括建设工程项目实施的管理组织和任务组织。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]