[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141410,799,1,"单选题","下列建设工程项目进度控制的措施中，属于经济措施的是（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","重视信息技术在进度控制中的应用",false,{"key":16,"text":17,"correct":14},"B","分析设计方案对工程进度的影响，优化设计方案",{"key":19,"text":20,"correct":21},"C","编制与进度计划相适应的资源需求计划",true,{"key":23,"text":24,"correct":14},"D","分析影响工程进度的风险，减少进度失控的风险量","本题考查的是项目进度控制的经济措施。为确保进度目标的实现，应编制与进度计划相适应的资源需求计划。选项A、D，属于管理措施。选项B，属于技术措施。参见教材49。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]