[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141409":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141409,799,2,"多选题","下列建设工程项目进度控制措施中，属于技术措施的有（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","深化设计，选用对实现目标有利的设计方案",true,{"key":16,"text":17,"correct":18},"B","建立图纸审查、工程变更管理制度",false,{"key":20,"text":21,"correct":18},"C","编制与进度计划相适应的资金保证计划",{"key":23,"text":24,"correct":14},"D","优化施工方案，合理选用机械设备",{"key":26,"text":27,"correct":18},"E","优化工作之间的逻辑关系，缩短持续时间","AD","本题考查的是项目进度控制的技术措施。选项C属于经济措施。选项B、E属于管理措施。参见教材49。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]