[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141408,799,1,"单选题","为赶上已拖延的施工进度，项目部决定采用混凝土泵代替原来的塔吊运输混凝土。该纠偏措施属于（ ）。( 2015真题 )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","管理措施",false,{"key":16,"text":17,"correct":14},"B","组织措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","技术措施",true,"本题考查的是项目进度控制的技术措施。施工技术、施工方法和施工机械的变更都属于技术措施。参见教材57。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]