[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141407":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141407,799,1,"单选题","下列建设工程项目进度控制的措施中，属于技术措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定各类进度计划的审批程序",false,{"key":16,"text":17,"correct":18},"B","优选工程项目设计、施工方案",true,{"key":20,"text":21,"correct":14},"C","选择合理的合同结构",{"key":23,"text":24,"correct":14},"D","选择工程承发包模式","本题主要考查项目进度控制措施。 B项：优选工程项目设计、施工方案属于技术措施的内容，故B项正确。 A项：属于组织措施，故A项错误。 CD项：属于管理措施，故CD项错误。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]