[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141406":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141406,799,1,"单选题","建设工程项目进度控制的技术措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","选择工程承发包模式",false,{"key":16,"text":17,"correct":18},"B","调整施工方法",true,{"key":20,"text":21,"correct":14},"C","设立进度控制工作部门",{"key":23,"text":24,"correct":14},"D","编制工程风险应急计划","本题考核的是项目进度控制的技术措施。 建设工程项目进度控制的技术措施涉及对实现进度目标有利的设计技术和施工技术的选用。 B项：B项属于技术措施，所以B项正确。 ACD项：AC项属于管理错误，所以ACD项错误。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]