[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141405":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141405,799,1,"单选题","下列为加快进度而采取的各项措施中，属于技术措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制进度控制工作流程",false,{"key":16,"text":17,"correct":14},"B","实行班组内部承包制",{"key":19,"text":20,"correct":21},"C","用大模板代替小钢模",true,{"key":23,"text":24,"correct":14},"D","重视计算机软件的应用","本题主要考查进度控制的措施。 建设工程项目进度控制中的四个措施如下： C项：用大模板代替小钢模是施工技术方案，属于技术措施，故C项正确。 A项：编制进度控制工作流程属于组织措施，故A项错误。 BD项：属于管理措施。故BD项错误。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]