[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141401":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141401,799,1,"单选题","下列建设工程项目进度控制的措施中，属于经济措施的是（ ）。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","落实资金供应条件",true,{"key":16,"text":17,"correct":18},"B","选择发承包模式",false,{"key":20,"text":21,"correct":18},"C","进行工程进度的风险分析",{"key":23,"text":24,"correct":18},"D","优选工程项目的设计、施工方案","本题考查的是项目进度控制的经济措施。建设工程项目进度控制的经济措施涉及资金需求计划、资金供应的条件和经济激励措施等。选项B属于管理措施；选项C属于管理措施；选项D属于技术措施。参见教材55。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]