[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141399":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141399,799,2,"多选题","建设工程项目进度控制的经济措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","编制项目进度控制的工作流程",false,{"key":16,"text":17,"correct":18},"B","经济激励措施",true,{"key":20,"text":21,"correct":18},"C","资金需求分析",{"key":23,"text":24,"correct":14},"D","承发包模式的选择",{"key":26,"text":27,"correct":14},"E","进行有关进度控制会议的组织设计","BC","本题主要考查项目进度控制措施。 BC项：属于经济措施的内容，故BC项正确。 AE项：属于组织措施，故AE项错误。 D项：属于管理措施，故D项错误。 综上所述，本题正确答案为BC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]