[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141397":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141397,799,1,"单选题","为实现进度目标而采取的经济激励措施所需要的费用，应在（ ）中考虑加快工程进度所需要的资金。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程预算",true,{"key":16,"text":17,"correct":18},"B","投标报价",false,{"key":20,"text":21,"correct":18},"C","投资估算",{"key":23,"text":24,"correct":18},"D","工程概算","本题主要考查项目进度控制的经济措施。 建设工程项目进度控制的经济措施涉及资金需求计划、资金供应的条件和经济激励措施等。在工程预算中应考虑加快工程进度所需的资金，其中包括为实现进度目标而采取的经济激励措施所需要的费用。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]