[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141396,799,1,"单选题","为确保工程项目进度目标的实现，应编制与进度计划相适应的资源需求计划，发现资源条件不具备，则应调整（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度目标",false,{"key":16,"text":17,"correct":14},"B","资源计划",{"key":19,"text":20,"correct":14},"C","资金计划",{"key":22,"text":23,"correct":24},"D","进度计划",true,"本题考核的是建设工程项目进度控制的经济措施。 建设工程项目进度控制的经济措施涉及资金需求计划、资金供应的条件和经济激励措施等。为确保进度目标的实现，应编制与进度计划相适应的资源需求计划（资源进度计划），包括资金需求计划和其他资源（人力和物力资源）需求计划，以反映工程实施的各时段所需要的资源。通过资源需求的分析，可发现所编制的进度计划实现的可能性，若发现资源条件不具备，则应调整进度计划。 综上所述，正确选项为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]