[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141393":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141393,799,2,"多选题","关于建设工程项目进度控制措施的说法，正确的有（ ） 2016",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对于工程项目的进度开展风险管理属于经济措施",false,{"key":16,"text":17,"correct":18},"B","各类进度计划的编制、审批程序属于组织措施",true,{"key":20,"text":21,"correct":14},"C","进度控制会议的组织设计属于技术措施",{"key":23,"text":24,"correct":18},"D","进度控制的管理措施涉及管理的思想、方法、和手段、承发包模式等",{"key":26,"text":27,"correct":18},"E","应用信息技术进行进度控制属于管理措施","BDE","本题考查的是建设工程项目进度控制的措施。选项A是管理措施，选项C是组织措施。参见教材54～155。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]