[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141390":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141390,799,2,"多选题","为顺利地实施建设工程项目的进度控制，项目管理者应当强化（ ）的管理理念。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","与供方互利",false,{"key":16,"text":17,"correct":18},"B","系统方法",true,{"key":20,"text":21,"correct":18},"C","动态控制",{"key":23,"text":24,"correct":18},"D","多方案比选",{"key":26,"text":27,"correct":14},"E","以顾客为关注焦点","BCD","本题考核项目进度控制的管理措施。 项目进度控制在管理观念方面应当强化进度计划系统观念、动态控制观念、多方案比选和选优的观念。 综上所述，正确选项为BCD。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]