[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141389,799,1,"单选题","在建设工程项目进度控制的管理措施中，直接关系到工程实施的组织和协调的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管理方法的选择",false,{"key":16,"text":17,"correct":18},"B","承发包模式的选择",true,{"key":20,"text":21,"correct":14},"C","合同类型的选择",{"key":23,"text":24,"correct":14},"D","信息管理的应用","本题主要考查进度控制的管理措施。 承发包模式的选择直接关系到工程实施的组织和协调。为了实现进度目标，应选择合理的合同结构，以避免过多的合同交界面而影响工程的进展。 综上所述，本题正确答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]