[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141387,799,1,"单选题","常见的影响工程进度的风险不包括（ ）风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织",false,{"key":16,"text":17,"correct":18},"B","资金时间",true,{"key":20,"text":21,"correct":14},"C","资源",{"key":23,"text":24,"correct":14},"D","合同","本题主要考查风险分析。 为实现进度目标，不但应进行进度控制，还应注意分析影响工程进度的风险，并在分析的基础上采取风险管理措施，以减少进度失控的风险量。常见的影响工程进度的风险，如：组织风险、管理风险、合同风险、资源（人力、物力和财力）风险、技术风险等。 本题为选非题，综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]