[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141386,799,1,"单选题","下列措施中，属于进度控制的管理措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整进度控制任务分工表",false,{"key":16,"text":17,"correct":14},"B","进行进度控制会议的组织设计",{"key":19,"text":20,"correct":21},"C","选择承发包模式",true,{"key":23,"text":24,"correct":14},"D","改进施工方法","本题主要考查项目进度控制措施。 C项：分析影响项目工程进度的风险属于管理措施的内容，故C项正确。 AB项：属于组织措施，故AB项错误。 D项：属于技术措施，故D项错误。 综上所述，本题正确选项为C项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]