[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141384,799,1,"单选题","下列进度控制措施中，属于管理措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建立进度控制的会议制度",false,{"key":16,"text":17,"correct":18},"B","分析影响项目工程进度的风险",true,{"key":20,"text":21,"correct":14},"C","制定项目进度控制的工作流程",{"key":23,"text":24,"correct":14},"D","选用有利的设计和施工技术","本题主要考查项目进度控制措施。 B项：分析影响项目工程进度的风险属于风险管理，是管理措施的内容，故B项正确。 A、C项：属于组织措施，故A、C项错误。 D项：属于技术措施，故D项错误。 综上所述，本题正确选项为B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]