[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141379":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141379,799,1,"单选题","下列进度控制措施中，属于组织措施的是（ ）。2014",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制工程网络进度计划",false,{"key":16,"text":17,"correct":14},"B","编制资源需求计划",{"key":19,"text":20,"correct":14},"C","编制先进完整的施工方案",{"key":22,"text":23,"correct":24},"D","编制进度控制的工作流程",true,"本题考查的是项目进度控制的组织措施。应编制项目进度控制的工作流程，如： （一）定义项目进度计划系统的组成； （二）各类进度计划的编制程序、审批程序和计划调整程序等。参见教材56。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]