[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141377":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141377,799,2,"多选题","下列进度控制的措施中，属于组织措施的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","选择承发包模式",false,{"key":16,"text":17,"correct":14},"B","进行工程进度的风险分析",{"key":19,"text":20,"correct":14},"C","落实资金供应的条件",{"key":22,"text":23,"correct":24},"D","编制项目进度控制的工作流程",true,{"key":26,"text":27,"correct":24},"E","进行有关进度控制会议的组织设计","DE","本题考查的是进度控制的组织措施的内容。 项目进度控制的组织措施主要有，应编制项目进度控制的工作流程，应进行有关进度控制会议的组织设计。 DE项：DE项属于组织措施，故当选。 AB项：AB项属于管理措施，故不当选。 C项：C项属于经济措施，故不当选。 综上所述，本题正确选项为DE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]