[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141376":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141376,799,2,"多选题","建设工程项目进度控制的主要工作环节包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","分析论证进度目标",true,{"key":16,"text":17,"correct":14},"B","跟踪检查进度计划执行情况",{"key":19,"text":20,"correct":21},"C","确定进度目标",false,{"key":23,"text":24,"correct":14},"D","编制进度计划",{"key":26,"text":27,"correct":14},"E","采取纠偏措施","ABDE","本题主要考查的是项目进度的控制。 建设工程项目进度控制包括进度目标的分析和论证，编制进度计划，进度计划的跟踪调查与校正。 综上所述，正确选项为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]