[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141375":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141375,799,1,"单选题","建设工程项目进度控制的主要工作环节不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","进度目标的分析和论证",false,{"key":16,"text":17,"correct":14},"B","采取纠偏措施",{"key":19,"text":20,"correct":14},"C","调整进度计划",{"key":22,"text":23,"correct":24},"D","评审设计方案",true,"本题考核的是进度控制的主要工作内容。 建设工程项目进度控制是一个动态的管理过程，其主要工作环节包括进度目标的分析和论证、编制进度计划、定期跟踪进度计划的执行情况、采取纠偏措施以及调整进度计划。 评审设计方案不属于进度控制的主要工作。 本题为选非题，综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]