[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141374,799,1,"单选题","建设工程项目进度控制工作包括：①编制进度计划；②调整进度计划；③进度目标的分析和论证；④跟踪检查计划的执行情况。其正确的工作程序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①-②-③-④",false,{"key":16,"text":17,"correct":14},"B","③-①-②-④",{"key":19,"text":20,"correct":21},"C","③-①-④-②",true,{"key":23,"text":24,"correct":14},"D","④-②-③-①","本题主要考查项目进度控制的组织措施。 进度控制的主要工作环节包括：进度目标的分析和论证－编制进度计划－跟踪检查计划的执行情况－调整进度计划。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]