[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141372,799,1,"单选题","项目进度控制的主要工作环节中，首先应进行的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制进度计划",false,{"key":16,"text":17,"correct":18},"B","分析和论证进度目标",true,{"key":20,"text":21,"correct":14},"C","定期跟踪进度计划的执行情况",{"key":23,"text":24,"correct":14},"D","采取纠偏措施","本题考查的是项目进度控制的组织措施的内容。 进度控制的主要工作环节包括进度目标的分析和论证、编制进度计划、定期跟踪进度计划的执行情况、采取纠偏措施。 从进度控制的工作环节可以看出，首先应进行的工作是分析和论证进度目标，故B项当选。 综上所述，本题正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]