[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141371":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141371,799,1,"单选题","下列措施中，属于进度控制的组织措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度控制会议的组织设计",true,{"key":16,"text":17,"correct":18},"B","利用网络方法编制工程进度计划",false,{"key":20,"text":21,"correct":18},"C","承发包模式的选择",{"key":23,"text":24,"correct":18},"D","更换施工机械","本题主要考查项目进度控制措施。 A项：属于组织措施的内容，故A项正确。 BC项：属于管理措施，故BC项错误。 D项：属于技术措施，故D项错误。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]