[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141366":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141366,799,1,"单选题","某工程双代号时标网络计划如下图所示（单位：周），工程E可以利用的机动时间是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","本题考核的是总时差的计算。 工作E的总时差为“在不影响总工期的前提下，工作E可以利用的机动时间”。E工作紧后工作有3个。在双代号时标网络中，波形线为时差。E工作的时差为2、4、7中最小值。所以为2。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]