[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141364":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141364,799,1,"单选题","在工程网络计划的执行过程中，监理工程师检查实际进度时，只发现工作M的总时差由原计划的2d变为-1d，说明工作M的实际进度（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拖后3d，影响工期1d",true,{"key":16,"text":17,"correct":18},"B","拖后1d，影响工期1d",false,{"key":20,"text":21,"correct":18},"C","拖后3d，影响工期2d",{"key":23,"text":24,"correct":18},"D","拖后2d，影响工期1d","本题主要考查时差的计算。 项目的总时差指一项工作在不影响总工期的前提下所具有的机动时间。M工作的总时差由2d变成了-1d，一共减少了3d，说明M工作的实际进度拖后了3d，但是M工作的总时差是2d，所以影响工期1d。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]