[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141363,799,1,"单选题","已知某工程双代号网络计划的计划工期等于计算工期，且工作M的开始节点和完成节点均为关键节点，则该工作（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","为关键工作",false,{"key":16,"text":17,"correct":18},"B","总时差等于自由时差",true,{"key":20,"text":21,"correct":14},"C","自由时差为零",{"key":23,"text":24,"correct":14},"D","总时差大于自由时差","本题主要考查双代号网络计划。 BD项：在双代号网络计划中，计划工期等于计算工期，完成节点为关键节点的工作，其总时差等于自由时差。所以B项正确，D项错误。 A项：在双代号网络计划中，计划工期等于计算工期，且开始节点和完成节点均为关键节点的工作不一定是关键工作。所以A项错误。 C项：在双代号网络计划中，计划工期等于计算工期，完成节点为关键节点的工作，如该工作为关键工作，则自由时差为0，否则自由时差不一定为0。所以C项错误。 综上所述，本题正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]