[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141362":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141362,799,1,"单选题","总时差指的是在不影响（ ）的前提下，本工作可利用的机动时间。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","紧后工作",false,{"key":16,"text":17,"correct":14},"B","持续时间",{"key":19,"text":20,"correct":14},"C","紧前工作",{"key":22,"text":23,"correct":24},"D","总工期",true,"本题主要考查总时差的概念。 总时差指的是在不影响总工期的前提下，本工作可利用的机动时间。 综上所述，本题正确选项为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]